Capenhurst, Urenco

Overview

Cara were employed again by Eric Wright Construction to carry out all re-enforced Concrete structure works, and installation of underground surface water storage tanks.

The structures were part of the uranium storage facility incorporating BLAST WALLS at 550 mm wide section. An Overhead Crane running track was incorporated into the external floor slab design for uranium placement.

This contract was completed ahead of programme to the approval of the Client.

Project Details

RLD, formation, reinforced concrete walls and structures, attenuation and associated drainage.

Division

Cara Nuclear

Client

Eric Wright Construction

Value

£530K

Duration

35 weeks