Chester RMD

Overview

Construction of a 58,000 sq. ft Rail Maintenance Depot. The contract also included external track Laying and construction of new carriage and under carriage washing facility.

A full length under vehicle inspection & maintenance pit was constructed in the floor slab. The site required 24 hour working patterns to accommodate the train time tables.

Completed on time, to budget, and to an excellent standard.

Project Details

Sub structure, drainage, reinforced concrete walls & structures and live trackwork.

Division

Cara Civil Engineering

Client

Eric Wright Construction

Value

£550K

Duration

32 weeks